Parker Flats April 3, 2008
From a future resident;
The garage door looks very tight, I was pleased with how it came out and to be honest, surprised. Actually saw Jay Voss up there when I was there today. Bad news for us, instead of starting on floors 2-3 for drywall, they are going to start in units 00-04 all the way up before moving to the southern part of the building. he said it is because of the penthouse and the roof hole they are unable to work on that side of the building.
Tags:Parker Flats Cincinnati Ohio
0 Comments:
Post a Comment
<< Home